The layout, and which wastes, toilets, showers and walls move
Moving a waste or a wall drives cost and every later stage.
Ask: Is anything that drains moving? Check the fall to the sewer before you commit.
57 decisions over 10 build stages, and the stage each one has to be made by. Most choices can wait. These cannot, because a later trade builds to them. Importing adds a lead time on top: 25 of them involve something made in China, and each shows the date to order it by.
Enter the day work starts on site. We fill a typical renovation program from it; change any stage to match your builder's program. Saved in this browser only.
Layout, what moves, and what has a long lead time. The cheapest stage to change your mind.
Moving a waste or a wall drives cost and every later stage.
Ask: Is anything that drains moving? Check the fall to the sewer before you commit.
The joinery is built around their cut-outs and clearances.
Ask: Do you have the spec sheet, with cut-out sizes, for every appliance?
Buy appliances in Australia: they need RCM and a local warranty. The joinery is drawn to their cut-outs.
It sets how the floor is built and how deep the screed is.
Ask: Can the floor be set down, or do you need a hob or linear drain to get the entry you want?
Each one needs framing, so it has to be known before the carpenter starts.
Ask: Which items sit in the wall rather than on it?
Some take weeks or months to arrive, longer than the gap to the stage that needs them.
Ask: What has a lead time longer than the time until it is needed?
The list of everything made overseas, with an order date for each. This page works it out from your program.
Livable housing rules, for example, apply differently by state and not at all in some. Source
Ask: Have you asked your certifier or builder which rules apply to this job?
Anything recessed or wall-hung. The carpenter frames to the actual product.
The carpenter frames the opening to the product. A different cabinet later means re-framing.
Ask: Is the cabinet in hand, or its spec sheet final? The framer needs the real size, not an estimate.
Lock the exact size at framing; the cabinet itself can follow in a later shipment.
It is framed now and tiled later, so its size should suit whole tiles. Source
Ask: Is the niche sized to whole tiles, clear of the mixer, and between studs? A common base height is 900 to 1100 mm.
The frame sets the pan height, the button height and the wall depth.
Ask: Which frame, and does it suit your pan and your wall depth?
The frame goes in at framing, so it rides in the first container, or comes from local stock of the same maker.
Wall-hung items need a frame or heavy blocking behind them.
Ask: What is hanging off the wall, and what does its install sheet ask for behind it?
Wall-hung toilets need their frame at framing. Vanities can follow with the joinery.
A floor-mounted filler can't be added once the floor is poured or screeded. Source
Ask: If the filler comes up through the floor, is its position fixed now?
A built-in bath goes in before waterproofing. A freestanding bath can follow at fit-off.
Openings are framed now. Where livable housing rules apply, doors need an 820 mm clear opening. Source
Ask: Which doors are sliders, and do the openings meet any rule that applies to you?
Internal doors and frames ride with the joinery. Cavity slider units are bought locally.
A sill that clips the splashback or the tap is a framing fix, not a tiling one.
Ask: Does every sill clear the bench, splashback and taps under it?
Windows and external doors: order straight after approval. Made in 35 to 45 working days, then shipped.
The duct runs through the ceiling or wall before linings. Over gas, the hood must be at least 650 mm above the cooktop. Source
Ask: Where does the duct go, and is the hood at least 650 mm above a gas cooktop?
Buy locally, but the duct route is set now.
Everything that sits in the wall or ceiling. Most variations start here.
In-wall mixer bodies are brand-specific. The trim must match the body already in the wall.
Ask: Is the trim you want the same brand as the body going in now?
In-wall mixer bodies go in at rough-in and the trims must be the same brand. WaterMark on the exact model, checked before you order.
The outlets are fixed in the wall. Roses usually sit 2000 to 2200 mm and mixers about 1000 to 1200 mm. Source
Ask: Rail or arm? Have you set the heights from the finished floor?
The in-wall parts are needed at rough-in; the rail or rose can follow.
It sets the falls and should sit on the tile grid.
Ask: Will the waste land on a tile joint, and which way does the floor fall to it?
Linear drains need WaterMark. Order with the tapware or buy locally.
It sets the waste and supply heights, and the spout is set off the basin rim. Tops usually sit 850 to 900 mm. Source
Ask: What height is the finished top, and how high is the basin rim above it?
Vanities and basins ride with the joinery.
Pans are set out at 140 or 165 mm from the wall. The waste is placed to suit the pan. Source
Ask: Which pan, and which set-out does its install sheet give?
The plumber sets out from the pan's install sheet at rough-in, so lock the model then; the pan itself can follow.
It sets pipe runs and power or gas. Water at basins, baths and showers is limited to 50 degrees C. Source
Ask: Where does the hot water unit go, and how far is the longest run?
Cables go in before the walls close. Power points are usually about 300 mm high and switches about 1000 to 1200 mm, by convention, not code. Source
Ask: Have you walked each room with the furniture: bedsides, desk, TV, benches, robe, appliances?
AS/NZS 3000 sets zones around showers and baths that limit what can go where. Source
Ask: Has your electrician checked every point near water against the wet-area zones?
Each needs a point at the height its install sheet gives, and the fan needs a duct.
Ask: Do you have the install sheet for each powered item?
Each sits at a position the appliance's spec sheet sets.
Ask: Is every appliance's point placed to its spec sheet, not a guess?
Each point sits where the appliance's install sheet says.
Outdoor power points must be at least 300 mm above the ground. Source
Ask: Where do you need power, water and light outside?
All run in the walls and ceiling. Smoke alarm rules differ by state.
Ask: Have you checked your state's smoke alarm rules, and where the AC drain runs?
Tile size, bedding depth and falls. Every height in the room is measured from the finished floor this sets.
It sets the joint lines, the cuts and where the waste sits. You can pick the exact colour later.
Ask: Do you know the tile size, so the floor and the waste can be set out?
The size is needed at set-out even if the colour comes later. Ask for an AS 4586 slip report on every floor tile.
Allow about 40 to 50 mm. It moves the finished floor, and every height in the room is measured from the finished floor.
Ask: Have you allowed 40 to 50 mm for bedding? Your heights are from the finished floor, not the slab.
About 15 to 25 mm is added to the wall face, which moves outlets, niches and set-outs. Source
Ask: Have pipe and outlet depths allowed for the finished wall face?
Wet-area falls are set by the NCC and AS 3740. Get them wrong and water sits or escapes. Source
Ask: Have your tiler and waterproofer agreed the falls and the shower entry?
Every fixture height is from the finished floor. Mark it once, then set out from it.
Ask: Is there a datum line on the studs before anything is set out?
Tile next to timber or carpet needs matching heights and a trim.
Ask: Do the finished floor levels line up at every doorway?
Membrane heights and details. Can't be redone once tiled.
Shower walls are waterproofed to at least 1800 mm (or 50 mm above the rose if higher), with 40 mm each side of wall junctions. Source
Ask: Does your waterproofer's scope meet the NCC heights?
These are the leak points, and they are buried once tiled.
Ask: Is every waste flanged, and is the niche sill falling back into the shower?
Blocking behind every fixing, and the plasterboard finish level.
Once the sheet is on, adding it means cutting the wall. Where livable housing rules apply, grab-rail walls need 12 mm ply or 25 mm noggings. Source
Ask: Has every fixing point got blocking, photographed before sheeting?
Level 4 is standard. Gloss paint, dark colours and raking light need Level 5, which is set when the board is stopped, not painted. Source
Ask: Are any walls going gloss, dark, or in raking light?
Wet areas take a water-resistant board under the membrane and tile.
Ask: Is wet-area board specified for every wet wall?
Tile heights, grout, trims and slip ratings. The tiler sets out from these on day one.
The tiler sets out from these. Keep one skirting height on every wall; a height that changes is the first thing people notice.
Ask: For each wall: floor to where?
Pale floor grout tends to go grey; epoxy needs no sealing and suits showers but costs more.
Ask: Have you seen the grout beside the real tile, in the room's own light?
Trims show on every external corner and should match the tapware finish.
Ask: Which edges get a trim, and in what finish?
Ship trims with the tiles so the finish matches.
Two trades meeting on one line shows every millimetre of tolerance. Keep the top of a mirror cabinet off the tile line, about 100 mm below it.
Ask: Do any edges from two different trades land on the same line?
P3 is the usual minimum for bathroom floors; P4 or P5 for outdoors, ramps and pool surrounds.
Ask: Does each floor tile carry a published P rating that suits where it goes?
A factory slip test to AS 4586 for every floor tile, before you order. P3 or better for a bathroom floor.
It meets the benchtop, the cupboards and the rangehood, so the junctions need deciding.
Ask: Where does the splashback stop at each end and at the top?
Stone or tile splashbacks ride with the benchtops.
Measure what was built, not what was drawn, then lock boards, benchtops and appliances.
Drawings can be well out. Laser-measure the finished walls, then order.
Ask: Have the cabinet sizes been checked against a site measure after linings?
Importing reverses this: the drawings are signed to the plan before the walls exist. Check the critical dimensions on site after framing.
The edge profile can move the price more than the colour does.
Ask: Which edge, which thickness, and where are the overhangs?
Factory-cut stone is cut to the shop drawings, so it is decided with the joinery. Engineered stone is banned.
Boards are ordered with the cabinets.
Ask: Have you seen the board sample next to the benchtop and the floor?
Sign the shop drawings 12 to 16 weeks before install. Many owners sign to the plan and accept a site check.
Stone is templated around the real sink, tap and cooktop. Without them, expect a return visit.
Ask: Are the sink, tap and cooktop on site when the templater comes?
No template on site: the factory cuts stone to the drawings, so the sink, tap and cooktop models must be on them.
Benches usually sit 900 to 950 mm, and the top of a wall oven no higher than about 1700 mm, by convention. Source
Ask: Have you checked the bench height against the tallest and shortest cook?
On the shop drawings, so it is fixed when they are signed.
Robes are ordered with the cabinets, and any lighting needs power at rough-in.
Ask: Long hanging, double hanging, drawers: how much of each?
Robes ride with the kitchen joinery.
Colours, sheen, prep and coats, per surface.
The painter quotes per surface.
Ask: Have you put real samples on your own walls, in the room's light?
Ceilings are usually flat, walls low sheen, and wet areas, trims and doors semi-gloss or gloss.
Ask: Is the sheen written next to every colour in the painter's scope?
Quotes differ most on prep and coats. Master Painters recommend three coats on new work. Source
Ask: Does every quote state the prep and the coats, so you can compare them?
Most houses are coloured from the roof down, and darker roofs run hotter.
Ask: Do the wall and trim colours work with the roof colour you have?
The choices you can safely leave late: positions are already fixed.
Positions were fixed at rough-in, so the fitting itself can be chosen late.
Ask: Do the fittings suit the points already in the ceiling?
A later shipment is fine. Every light needs RCM before it is installed.
The blocking is already in, so these can wait.
Ask: Do the finishes match the tapware?
A later shipment is fine.
Screens are measured after tiling.
Ask: Has the screen been measured off the finished tiles?
Shower glass must meet AS 1288: ask for the test report. Can follow in a later shipment.
Nothing else depends on them.
Ask: Did the power points land where the furniture went?
Prompts, not rules. Code items cite their source; states adopt parts of the NCC differently, so check yours. Your builder, trades, certifier and each product's install sheet decide. Order dates assume 16 weeks from order to site, the planning figure for a China-made fit-out; your factory's lead time on the Project Plan replaces it.